How do I enter a Project Summary Task into a Microsoft Project schedule?

A Project Summary Task is a placeholder for the project name. The Project Summary Task has a zero ID number. This lesson covers entering a Project Summary Task into a Microsoft Project schedule.

1. Click the Format Tab

  1. Click the Format tab.
  2. Click under the Task Name column where the Project Summary Task will appear.

2. Check the Project Summary Task Box

  • From the Format tab, check the Project Summary Task box on the ribbon.

3. Type the Project Name

  1. Type theproject name in the task grid.
  2. View the 0 Task ID number to the far left.