How do I assign resources using the Split Screen view in Microsoft Project?

This lesson covers assigning resources using the Split Screen view in Microsoft Project.

Click the Task Tab

  • Click the Task tab.

Click Details

  • Click Detailson the ribbon.

Select a Task

  • Select a task for which a resources will be assigned.

Click in Resource Name Column

  1. Click in the Resource Name column.
  2. Click in the Resource Name box.
  3. Select the resource name.

Click OK

  • Click OK. Repeat as needed.

Click Details

  • To remove the split screen, click the Details button on the ribbon.

View the Resource Assignments

  • View resource names in project schedule and in the Gantt Chart.