How do I mark My Work items as complete?

Updating a My Work item can be done from the Home Page or from the My Work Center. Updates from the My Work Center will be shown below. To mark an item as complete in My Work, check the box to the left of the work item.

Check the Box

131.png
  • To mark a work item as complete, check the box located to the far left of the item. Once you check the box, the item will be removed from the list.

Note: Check boxes that appear pink indicate the items are overdue.

Click in the Due Date Column to Update the Finish Date

Click in the Due Date Column to Update the Finish Date
  • Click the date calendar box to update the finish date of a task and select the date in the calendar.

View Items Marked as Completed

132.png
  • Click the Show Completed button on the ribbon below the Views tab. The check marks indicate the items are complete.

Note: The Completed link on the Filter Toolbar may be used as well.

View the Completed Work Items List

133.png
  • View the Completed Work Items list.