Iterations are your time frames. After you create an iteration, then start moving items from the backlog into the iterations. A backlog item is a container for defects, user stories, and tasks. Backlog items are moved into a specific iteration within the Project Agile Planner. This article covers moving a backlog item inside the Project Agile Planner into a specific iteration.

1. Drag the Backlog Item up to the Top Grid

  1. Select the backlog item in the bottom grid.
  2. Drag the backlog item up into the top gird until a blue arrow appears to the left of the iteration name. Release your mouse.

2. View the Backlog Item Below the Iteration

  • View the backlog item listed below the iteration.